Mr. Tim Van Driel, Manager - Civic
Building Projects, provided the following updates regarding the major civic
building projects:
·
Burnaby
Lake Aquatic and Arena Facility/C.G. Brown Memorial Pool (awarded contract to
HCMA for Phase I with an option to proceed to Phase II, and hired a
geotechnical engineer);
·
Willingdon
Heights Community Centre (report coming to Council to recommend the contract
award, hired a geotechnical engineer, and completed the environmental site
assessment);
·
Confederation
Community Centre/Eileen Dailly Pool (hiring a geotechnical engineer,
completed the environmental site assessment, and architect request for
proposal (RFP) closes in May 2019);
·
Cameron
Community Centre (completed the environmental site assessment, geotechnical RFP
will be issued in May 2019, and architect RFP will be issued in summer 2019);
·
South
Burnaby Ice Arena (tender to prequalified general contractors closes in May
2019, recommendation to Council is forthcoming in May 2019, and building
permit and preliminary plan approval drawings updated with rezoning changes);
·
Child
Care – Montecito and Capitol Hill Elementary Schools (working with modular
building manufacturer regarding the materials, and general contractor is
proceeding with civic construction);
·
Child
Care – Stride Avenue Community School (the design method changed to
stick-frame construction, see Item 5 (j) on the agenda);
·
Child
Care – Cascade Heights Elementary (project on hold until an alternative
location is selected);
·
Emergency
Generators at Civic Facilities (proceeding at Bonsor Recreation Complex and
Edmonds Community Centre, and a report to the Committee is forthcoming);
·
Laurel
Street Works Yard Phase I – Yard Building (the building will be completed in
May 2019);
·
Laurel
Street Works Yard Phase II – Main Building (consultant team is finalizing
tender documents, second public Open House was held in April 2019, and additional
environmental investigations are ongoing);
·
Edmonds
Community Centre Pool Gutter Replacement (completed);
·
RCMP
Interior Renovation (Phase I (records room) is complete, Phase II (watch
commander) will be completed in April 2019, and Phase III (former operational
communications centre) will be completed in May and June 2019);
·
RCMP
Drug Lab (detailed design RFP closed and architect will be hired in April
2019);
·
Metrotown
Events Centre (in preliminary stages of RFP for conceptual design);
·
Burnaby
Lake/Deer Lake Pedestrian Overpass (Parks, Recreation and Culture Commission
approved funding for a feasibility study); and
·
Covered
sports boxes.
The Committee inquired regarding the
completion of the covered sports boxes project.
Staff advised that soil testing at the
Central Valley Greenway identified contamination and logistic problems, and
they are evaluating covering two existing sports boxes at Confederation Park
and Riverway Sports Complex.
Arising from discussion and without objection
by any member, the Committee requested that staff note the target completion
date for the current phase of the major civic building projects in future
project status updates.
Staff undertook to follow-up.
The Committee inquired regarding
delays in creation of child care spaces at Stride Avenue Community School and
Cascade Heights Elementary.
Staff advised that delays are due to
unanticipated, additional funding provided by the Provincial Government to the
School District for modular units and pre-school and after-school care, which
has resulted in changes to locations for the child care facilities.
|